44+400 VUP Junction BC laying 47+300 median plantation watering 53+200 to 500 RHS thermoplastic road marking
Progress Photographs During 1st week of October-2026
42+300 authorised median opening, solar blinker yellow light fixing .56+000 VASD Equipments fixing 53+210 to 53+500 RHS MCW BC laying…
Progress Photographs During 4th week of September-2026
Full VMS Gantry boards 38+250 LHS ATMS full (VMS) gantry fixing
Progress Photographs During 3rd week of September-2026
53+400 ROB P1 to P2 deck slab safety consultant site visit 38+800 RHS compact VMS cantilever fixing 44+855 RHS Service…
Progress Photographs During 2nd week of September-2026
53+400 ROB RHS gap slab 53+400 ROB P1-P2 RHS Deck slab 41+250 to 42+500 LHS unline drain cutting Asphalt sheet…
Progress Photographs During 1st week of September.-2026
39+000 to 39+200 median cleaning.
Progress Photographs During 4th week of August-2026
DGPS and Drone analytics survey is in progress 37+050 LHS OVER HEAD GANTRY BOARD FIXING WORK IN PROGRESS 44+400 load…
Progress Photographs During 3rd week of August-2026
53+400 ROB LHS A1 Abutment Dirt Wall bracket Shuttering work in progress 53+400 ROB LHS A2 side Gap slab staging…
Progress Photographs During 2nd week of August-2026.
Ch 53+400 ROB RHS A2side Bowstring lifting work in progress ( 7.2 metre lifting has done) Ch 53+400 ROB LHS…
Progress Photographs During 1st week of August-2026.
Re panel Erection in progress at 63+200 wall 3 57+100-Major Bridge – load test – Unloading process from 100-75% completed…