Ch 53+400 ROB RHS A2side Bowstring lifting work in progress ( 7.2 metre lifting has done)
Ch 53+400 ROB LHS A1 Abutment Dirt Wall 1st lift shuttering work in progress Sir
39+940 MJB LHS P2 to P1 &P1 to A1 deck sheet fixing WIP
44+400 VUP RHS Dirt wall shuttering fixing WIP
44+400 VUP RHS Dirt wall shuttering fixing WIP
37+900 toll plaza PTZ camera’s erection done’
37+900 toll plaza high mast installation wip
ch37+900 toll plaza We have set up an PTZ camera pole LHS/RHS.
Friction slab Erection work in progress
Ch 53+400 ROB RHS A2side Bowstring lifting work in progress ( 8.4 metre lifting has done)
Ch-39+940 MJB span P1-P2 LHS reinforcement wip.
39+940 re wall approach soil compaction
Ch 55+113 VUP RHS A1 side gap slab beam steel fixing work in progress.
Ch 53+400 ROB RHS (P2 ,A2 Span )slab staging work in progress
Ch 53+400 ROB RHS (P2 ,A2 Span )slab staging work in progress Sir
Ch 53+400 ROB LHS A1 Abutment Dirt Wall 1st lift concrete pouring wip Sir
Ch 44+400 VUP RHS A2 abutment Dirt Wall 1st lift concrete completed
Ch 53+400 ROB LHS A2 abutment Dirt Wall bracket shuttering work in progress
Ch 54 +140 MNB RHS MCW A1 Abutment Dirt Wall bracket steel placement work in progress
Ch 55+113 VUP RHS A1 side Gap slab beam steel placement and shuttering work in progress
63+130 to 63+240 LHS Road widening & R.E wall. Level pad pcc works at PUP A2 side
DBM LAYING AT KM 44020-44370 RHS
DBM LAYING AT KM 44020-44370 RHS
RPM/ Studs fixing work is in progress at ch 51+300LHS
63+130 to 63+240 LHS R.E wall excavation & panal errection wip
63+130 to 63+240 LHS R.E wall excavation & panal errection wip
53 ROB Gap slab work in progress
WMM Laying work is in progress at chainage 52+660 to 52+760 LHS.
55+113 VUP RHS A1 side Gap slab progress Sir
63+130 to 63+200 LHS wall-3 R.E wall errection

ROB
39+940 RE wall Approach




RE wall of 39+940