MEIL ANANTHAPUR ROADWAYS PRIVATE LIMITED
About Project
4 Laning of NH 544D from existing km 39.380 of NH 544D (Design Chainage km 37.000) to km 74.450 (Design Chainage km 69.000) of Mutssukota —Bugga section of NH-544D on Hybrid Annuity Mode under NH (0), in the state of Andhra Pradesh.
Note: The duration for the construction of the project is 730 days from the appointed date with 15 years of operation and maintenance period.
Scope of the Project
30 No’s
Box/Pipe Culverts
10 No’s
Vehicular Underpass
2 No’s
Light Vehicular Underpass
11 No’s
Minor Bridges
2 No’s
Major Bridge
Project details and Timeline
4 Laning of NH 544D from existing km 39.380 of NH 544D (Design Chainage km 37.000) to km 74.450 (Design Chainage km 69.000) of Mutssukota —Bugga section of NH-544D on Hybrid Annuity Mode under NH (0), in the state of Andhra Pradesh.
Role/Type | Details |
---|---|
EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
Independent Engineer | M/s. Satra Services and Solution Pvt. Ltd |
Agreement Date | 03rd Feb 2023 |
Appointed Date | 17th Aug 2023 |
Maintenance Period | 15 Years after commencing |
COD Construction Period | 24 Months (730 days) from Appointed Date |
Project Cost | 733.35 Crs. |
Project highlights
- 4 Laning of NH 544D from existing km 39.380 of NH 544D (Design Chainage km 37.000) to km 74.450 (Design Chainage km 69.000)
- Comes under design, build, operate and Transfer (the DBOT Annuity or Hybrid Annuity).
- Part of Anantapur-Guntur National Highway.
- Design speed of section is 100kmph.
- Provides safe travel and reduce travel time.
Recent updates
Construction of bridge is completed at highway
Construction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of…