53+400 ROB LHS A1 Abutment Dirt Wall bracket Shuttering work in progress
53+400 ROB LHS A2 side Gap slab staging and fly board fixing work in progress
39+940 MJB LHS P2 to P1 & P1 to A1 deck slab top reinforcement fixing WIP
55200 RHS BUILDING DISMANTLE WIP
Unloading of the test load from 25% to 0% has been completed successfully with the IE team
Unloading of the test load from 25% to 0% has been completed successfully with the IE team






IE visit
57+100 RHS, Span p16–P17: Vehicle load testing is being conducted. Temperature correction has been started jointly with the IE team.