Ch 39+940 MJB LHS A2 abutment wall 2nd lift shuttering work in progress Ch 53+400 ROB A1 LHS side bowstring…
Progress Photographs During 2nd week of March-2026
Ch 39+842 VUP LHS A2 wall 3rd lift concrete pouring work in progress MCW ctsb laying work in progress @46+520…
Progress Photographs During 1st week of March-2026
46+680 to 46+800 Bhs merging DBM laying and rolling work in progress Ch 43+353 VUP LHS slab concrete pouring work…
Progress Photographs During 4th week of February-2026
BC laying and rolling work in progress @45+500 to 45+900 Bhs merging 54+140 MN RHS SR A2 to P1 slab…
Progress Photographs During 3rd week of February-2026
Service road and merging wmm top laying and rolling work in progress @46+500 to 46+750 RHS 55+500 DTR shifting and…
Progress Photographs During 2nd week of February-2026
MCW BC rolling work in progress @68+580 to 69+000 RHSMCW BC laying and rolling work in progress @68+250 to…
Progress Photographs During 1st week of February-2026
Service road BC laying work in progress @52+600 to 52+700 RHS Ch 39+842 VUP RHS slab reinforcement tying wip39+842