MCW DBM laying work in progress @43+140 to 43+480 LHS Ch 53+400 ROB LHS A2 side P2-A2 deck slab BE…
Progress Photographs During 2nd week of July-2026
MCW wmm laying and rolling work in progress @43+140 to 43+340 LHS W2 closing panel errection work started from 44+320…
Progress Photographs During 1st week of July-2026
Ch 39+940 MJB A1-P1 LHS girder erection work in progress LHS ROB -53+400-Transverse pushing/ slewing work completedLHS ROB -53+400-Transverse pushing/…
Progress Photographs During 5TH week of MAY-2026
Slope Preparation at 56+450 Ch 51+510 LHS overhead Gantry board column curing in processing. BC Laying work in progress @58+140…
Progress Photographs During 3rd week of June-2026
50+450 VUP Junction Geo strap fixing in progress at 54+850 lhs wall 1 Ctsb laying in progress at 55+450 lhs…
Progress Photographs During 2nd week of June-2026
CH-44+400 VUP RHS span A1-A2 Deck slab reinforcement cheking by BE sir. Ch 50+210 to ch 50+ 270 RHS wall-2…
Progress Photographs During 1st week of June-2026
Rolling in progress at 62+970 to 63+050 lhs Median wall excavation jn progress at 54+140 mnb Ch 53+400 ROB LHS…