MCW DBM laying work in progress @43+140 to 43+480 LHS
Ch 53+400 ROB LHS A2 side P2-A2 deck slab BE sir checking completed.
53+400 Rob P2 to A2 LHS Deck slab concrete pouring WIP
Ch 53+400 ROB LHS A2 side P2-A2 deck slab concrete finishing work is in progress.
50+500 median drain excavation Wip
44+030 to 44+050km RHS grading WIP
54+350 median slope cutting lhs wip
39+855 to 39+901 LHS wall-3 filter media pouring WIP
63+100 wall-3 levelling pad excavation Wip
46+360 to 46+500 bhs emb layer rolling wip
44+420 to 44+480 BHS EMB layer sheep foot Rolling WIP
44+420 to 44+480 BHS emb layer watering WIP
52+660 to 52+800 rhs mcw WMM top laying and rolling work in progress
Ch 53+400 Rob LHS A1 ,P1 Span slab steel placement work in progress Sir
At 39+842vup Rewall W3 4th layer errection work is going on.
50+750 median drain excavation Wip
44+400 junction Excavation WIP
44+420km to 44+500km RHS EMB layer soil unloading (GRK INF) WIP
54+950 to 55+000 LHS wall-1 Geo strip pulling WIP
52+400 median drain excavation Wip
44+430 to 44+500 RHS grading WIP

52+900 filter media unloading