Progress Photographs During 3rd week of July-2026

MCW DBM laying work in progress @43+140 to 43+480 LHS

Ch 53+400 ROB LHS A2 side P2-A2 deck slab BE sir checking completed.

53+400 Rob P2 to A2 LHS Deck slab concrete pouring WIP

Ch 53+400 ROB LHS A2 side P2-A2 deck slab concrete finishing work is in progress.

50+500 median drain excavation Wip

52+900 filter media unloading

44+030 to 44+050km RHS grading WIP

54+350 median slope cutting lhs wip

39+855 to 39+901 LHS wall-3 filter media pouring WIP

63+100 wall-3 levelling pad excavation Wip

46+360 to 46+500 bhs emb layer rolling wip

44+420 to 44+480 BHS EMB layer sheep foot Rolling WIP

44+420 to 44+480 BHS emb layer watering WIP

52+660 to 52+800 rhs mcw WMM top laying and rolling work in progress

Ch 53+400 Rob LHS A1 ,P1 Span slab steel placement work in progress Sir

At 39+842vup Rewall W3 4th layer errection work is going on.

50+750 median drain excavation Wip

44+400 junction Excavation WIP

44+420km to 44+500km RHS EMB layer soil unloading (GRK INF) WIP

54+950 to 55+000 LHS wall-1 Geo strip pulling WIP

52+400 median drain excavation Wip

44+430 to 44+500 RHS grading WIP

39+855 to 39+900 LHS emb layer rolling WIP