Tollplaza A1 30 mtr Highmast supply charged
44+400 vup RHS A2 side Gap slab steel placement work in progress Sir
53+400 ROB LHS A1 side Gap slab concrete pouring wip
Toll plaza
57+100-Major Bridge – load test for the Span A1-P1 LHS -25% of test placed
Ch. 55+200 RHS,SR house dismantling work is in progress




Ch. 57+100 RHS MJB — Third-party NDT Rebound Hammer and Ultrasonic Pulse Velocity (UPV) tests are in progress jointly with the IE team Sir.