MCW wmm laying and rolling work in progress @43+140 to 43+340 LHS
W2 closing panel errection work started from 44+320 to towards 44+380
44+300 to 44+380 LHS emb layer grading WIP
44+480 RSR b.c soil excavation Wip
50+050km median drain Excavation WIP
52+680 to 52+800 rhs mcw sg top rolling wip
Ch 53+400 ROB LHS A1,P1 Span slab Deck sheet fixing and middle diaphragm cross Girder
Ch 49+650 RHS median plantation watering
Chainage 46+600 to 46+620 RHS grade separator WIP sir
46+600 to 46+620 RHS grade separator WIP sir
MCW DBM laying and rolling work in progress @50+225 to 50+435 RHS
44 A2 rsr b.c soil excavation Wip
50+050km median drain Excavation WIP
44+460 to 44+500 bhs watering wip
44+280 to 44+370km BHS sheep foot rolling WIP
39+855 wall-3 emb layer grading wip


44+300km LHS bed watering WIP