Ch 51+510 LHS overhead Gantry board column curing in processing.
BC Laying work in progress @58+140 to 58+360 Lhs merging 58+970 to 59+180 Lhs merging
Ch 31+050 Overhead Gantry board column curing in processing..
Bus Shelter Erection Work in Progress at km 63+700. BHS Side
Ch 60+850 median plantation curing work in processing.
44+100 to 44+150 wall-2 3rd layer closing panel erection wip
LHS Wall-1 finishing and rolling works are currently in progress from Ch. 54+750 to Ch. 54+970.
BC Laying and rolling work in progress @58+140 to 58+360 Lhs merging 58+970 to 59+180 Lhs merging
Ch-44+400 VUP RHS deck slab casting has been done .
Wmm top rolling working in progress At 54+670 to 770 LHS service road.
Ch 46+500 to ch 46+350 RHS service road S.G Top Rolling work in progress sir
44+050 to 44+300 wall-2 emb 12 th layer Sheep foot rolleing wip
Ch59+500 To 59+850 (BHS) Thermoplastic road marking Work in progress Sir.
Ctsb laying in progress at 46+450 rhs service road
Service road S.G top preparation in progress at 46+450
ch44+400 vup LHS Deck slab curing work is in progress
BC Laying and rolling work in progress @62+020 to 62+240 Lhs
58+140 to 58+360 Rhs merging
embankment 26th layer watering work is in progress from Ch. 54+900 to Ch. 55+080 on LHS Wall-1.
BC Laying and rolling work in progress @58+140 Rhs merging
59+180 Rhs merging 60+300 Rhs merging

Slope Preparation at 56+450
Ch 37+900 Toll plaza Lane 2 to 7 WIM frames and rain water drainage pipe installation and IR foundation and Reader foundation work in progress
37+900 Toll plaza Lane 2,3,4,&5 WIM portion PQC laying has done and IR foundation wire rooting work in progress for all lanes 2 to 7