Progress Photographs During 3rd week of June-2026

50+450 VUP Junction

Geo strap fixing in progress at 54+850 lhs wall 1

Ctsb laying in progress at 55+450 lhs service road

Slope Preparation at 56+450

Ch 51+510 LHS overhead Gantry board column curing in processing.

BC Laying work in progress @58+140 to 58+360 Lhs merging 58+970 to 59+180 Lhs merging

Ch 31+050 Overhead Gantry board column curing in processing..

Ch 37+900 Toll plaza Lane 2 to 7 WIM frames and rain water drainage pipe installation and IR foundation and Reader foundation work in progress

Bus Shelter Erection Work in Progress at km 63+700. BHS Side

Ch 60+850 median plantation curing work in processing.

44+100 to 44+150 wall-2 3rd layer closing panel erection wip

LHS Wall-1 finishing and rolling works are currently in progress from Ch. 54+750 to Ch. 54+970.

BC Laying and rolling work in progress @58+140 to 58+360 Lhs merging 58+970 to 59+180 Lhs merging

Ch-44+400 VUP RHS deck slab casting has been done .

Wmm top rolling working in progress At 54+670 to 770 LHS service road.

Ch 46+500 to ch 46+350 RHS service road S.G Top Rolling work in progress sir

44+050 to 44+300 wall-2 emb 12 th layer Sheep foot rolleing wip

Ch59+500 To 59+850 (BHS) Thermoplastic road marking Work in progress Sir.

Ctsb laying in progress at 46+450 rhs service road

Service road S.G top preparation in progress at 46+450ch44+400 vup LHS Deck slab curing work is in progress

BC Laying and rolling work in progress @62+020 to 62+240 Lhs
58+140 to 58+360 Rhs merging

embankment 26th layer watering work is in progress from Ch. 54+900 to Ch. 55+080 on LHS Wall-1.

BC Laying and rolling work in progress @58+140 Rhs merging
59+180 Rhs merging 60+300 Rhs merging

37+900 Toll plaza Lane 2,3,4,&5 WIM portion PQC laying has done and IR foundation wire rooting work in progress for all lanes 2 to 7

 