Ch 39+842 VUP LHS A2 wall 3rd lift concrete pouring work in progress
MCW ctsb laying work in progress @46+520 to 46+620 LHS
Ch 39+940 MJB LHS A2 abutment Raft steel placement work in progress
Service road BC laying work in progress @44+500 to 44+710 Bhs
Ch 46+520 to 620 RHS MCW WMM top layer laying on progress
MCW DBM laying work in progress @53+170 to 53+340 Bhs

Ch 53+400 ROB A1 LHS side bowstring girder BLB joint plate welding work and Arch-3 placing and alignment work is in progress.