CH-44+400 VUP RHS span A1-A2 Deck slab reinforcement cheking by BE sir.
Ch 50+210 to ch 50+ 270 RHS wall-2 22nd layer watering work in progress sir
CH-44+400 VUP RHS span A1-A2 Deck slab reinforcement cheking by BE sir.
Ch 53+400 ROB LHS A1 Bowstring Lifting work in progress (9.8M lifting has done).
Ch50+900 To 52+350 (BHS)
Thermoplastic road marking work in progress Sir.
CTSB laying and rolling work in progress @54+660 to 54+950 LHS service road
44+150 to 44+200 wall-2 3 rd layer erection wip
43+600 A2 filtermedia unloading
MCW wmm Laying and rolling work in progress @50+100 to 50+180 Rhs
Ch 57+100 Re pannel casting work in progress
MCW wmm rolling work in progress @50+100 to 50+180 Rhs
Junction cutting in progress at under the vup at 43+350
44+290 to 44+380 wall-1 7 th layer erection wip
At 43+350vup Rewall A1 W1 panel errection work is going on
Ch 44+400 VUP LHS A1 A2 Span slab steel placement work in progress Sir
44+050 to 44+300 RSR emb layer finishing wip
44+150 to 44+380 rhs emb layer sheep foot rolling wip
Ch 47+500 A1 RHS side plantation fertilisation work in processing.

39+820 LSR cutting wip
Inspection of MJB Expansion Joint at Chainage 57+100 (RHS) was conducted and the installation workmanship was verified.
RE panel erection work for the closing layer of LHS Wall-1 is in progress from Ch. 54+730 to Ch. 54+780.