Rolling in progress at 62+970 to 63+050 lhs
Median wall excavation jn progress at 54+140 mnb
Ch 53+400 ROB LHS A1 Bow String Lifting work in progress (7.2M lifting has done)
Ch63+000 To 66+000(BHS) MCW Shoulder Line& Kerb Lane Road marking work in progress
Ch 39+940 MJB girder 04 Span P1-P2 LHS concrete pouring work in progress
44+300 to 44+380 bhs emb layer grading wip
44+300 to 44+380 bhs emb layer sheep foot rolling wip
Ch 39+940 MJB girder 04 Span P1-P2 LHS concrete pouring work in progress
Shoulder preparation in progress at 42+300
55+700 to 55+850 LHS MCW CTSB top laying in progress
62+850 Junction Cutting in progress
44+300 to 44+380 bhs emb layer grading wip
Sg top rolling in progress at 50+460
63+600 To 66+000(BHS) MCW Shoulder Line & Centre Line Road marking work in progress Sir.
MCW DBM laying and rolling work in progress @55+690 to 55+860 RHS
55+970 to 56+080 LHS
43+260 to 43+340 rhs emb layer sheep foot rolling wip
Chainage 46+400 A2 side pipe line WIP.
47+920 To 48+160 Grade Separator Portion Chute drains WIP DGM Sir visiting
MCW BC laying work in progress @56+300 to 57+800 LHS
BC MCW rolling work in progress @57+330 LHS
43+260 to 43+340 bhs emb layer sheep foot rolling wip
MCW BC laying and rolling work in progress 55+860 to 57+330 LHS

47447 BHS CROSS ROAD
50447 BHS CROSS ROAD

44 +050 to 44+150 wall-2 2nd layer erection wip