ch37+900 line 5 PQC laying work is in progress at toll plaza
ch37+900 toll plaza line 5 PQC laying work is in progress
Ch 53+400 ROB A1 side bowstring girder lifting work is in progress Till now 5.2m lifting has done
MCW CTSB Laying work in progress @52+930 to 53+040 Lhs
Ch 39+940 MJB RHS P1 Pier cap concrete pouring work in progress
MCW DBM Laying and rolling work in progress @44+740 to 44+820 Bhs
Ch 52+700 to 52+823 wall 1 LHS embakment 19 layer watering wip
44+420 to 44+480 wall-4 6th layer erection wip
Chainage 50+460 to 50+530 A2 side wall 3 LHS 35th layer rolling wip
CH50+400 To CH50+433 FS Bottom Bed Preparation WIP At LHS
39+940 MJB RHS A1 abutment wall final lift shuttering work in progress
44+400 VUP RHS A1, A2 Span slab staging work in progress
45+300 highway electrical lighting concrete foundations curing work
41+200 sign boards concrete foundations curing work in processing
37+050 Gantry sign board concrete foundation curing work
68+900 To 68+320(BHS) MCW Thermoplastics Road marking work in progress
Central Railway ADEN visited at site and gave concrete permission for track center footings
41+000 to 42+300 LHS sign board footings curing
MCW DBM Laying and rolling work in progress @59+530 to 59+780 Bhs