Service road and merging wmm top laying and rolling work in progress @46+500 to 46+750 RHS
55+500 DTR shifting and Lt line shifting work completed sir
MCW DBM laying work in progress @42+880 to 43+080 LHS 43+000 to 43+090 RHS
Girder 01 Span P1-A1 RHS concrete pouring work in progress of Ch 39+940 MJB
Ch 39+710 BC LHS MCW along with wall 2nd lift concrete pouring work has done
41+910 To 42+150 LHS Truck Lay-bye SG Top layer watering

Ch 44+400 VUP LHS A2 Abutment foundation raft vertical reinforcement placing and binding work in progress